Site construction work is well underway and Sunninghill are progressing well with the project.

 

The building itself is a steel framed, partly braced and partly sway frame, with concrete composite upper floors. It has a reinforced concrete piled raft ground slab and foundation.

 

The civil engineering, the foul water will connect into the existing extensive network to discharge and the surface water will be collected on a blue roof and attenuation tanks before it discharges to the existing network and the pond. Some local site SUDs features have been added with opening up of an existing culvert to create an open water course. Exceedance water flows will follow the original direction along the boundary location.